§5-22B-12. Criteria for evaluation.

(a) The evaluation committee shall evaluate proposals taking into consideration the criteria set out in this section with the maximum percentage of total points for evaluation which may be assigned to each criterion as set forth in this section. The following criteria shall be evaluated, when applicable:

(1) The financial resources of the construction manager to complete the project, 10 percent;

(2) The ability of the proposed personnel of the construction manager to perform, 20 percent;

(3) The character, integrity, reputation, judgment, experience, and efficiency of the construction manager, 20 percent;

(4) The quality of performance on previous projects, 20 percent;

(5) The ability of the construction manager to perform within the time specified, 10 percent;

(6) The previous and existing compliance of the construction manager with laws relating to the contract, 10 percent; and

(7) Such other information as may be secured having a bearing on the selection, 10 percent.

(b) The records of the evaluation committee in evaluating proposals and making recommendations shall be considered public records for purposes of §29B-1-1 et seq. of this code.